Skip to main content

Learn about our projects


Share this page

Rapid growth

Suvic operates nationwide in Finland. In addition to Finland, the company actively seeks growth opportunities in the Nordic markets, keeping the door open for opportunities elsewhere in Europe as well.
Despite being young, the company has compiled an impressive portfolio of expertise in energy construction: the company has a couple decades’ worth of experience in wind power alone, for example. The company has experience in structural engineering, electrical grids, budgeting, materials and subcontracting, as well as construction business.

Ongoing projects

Kirkkonummi data center waste heat power plant Kirkkonummi data center waste heat power plant

Kirkkonummi data center waste heat power plant

Fortum Power and Heat Oy
Completion: 2025

The Working Association Tricon-Suvic is the main contractor of the project and is responsible for construction of the buildings, heat-sink-battery foundations and constructing the pumping station. The principal of the work is Fortum Power and Heat Oy and the waste-heat-to-energy power plant will provide energy to Fortum’s district heating system in Kirkkonummi. The work will commence in autumn 2023 and will continue until the end of 2025.

Sandbacka wind farm Uusikaarlepyy & Vörå Sandbacka wind farm Uusikaarlepyy & Vörå

Sandbacka wind farm Uusikaarlepyy & Vörå

Prime Capital
Completion: 2023-2024

The project involves constructing infrastructure for 14 wind turbines, including the construction of the foundations and the internal grid. Sandbacka wind farm covers an area of approximately 680 hectares. The infrastructure work will be carried out using Suvic’s own land construction equipment.

Lappfjärd wind farm exansion Kristinestad Lappfjärd wind farm exansion Kristinestad

Lappfjärd wind farm exansion Kristinestad

Prime Capital
Completion: 2023

Suvic will build the foundations and the internal grid for the expansion of the Lappfjärd wind farm. The production capacity of the expansion part is 58 MW, which increases the total capacity of the wind farm to 250 MW. The rocky soil of the area enables the construction of all the foundations of the extension part as rock anchor foundations.

Isokangas - Palokangas wind farms Isokangas - Palokangas wind farms

Isokangas - Palokangas wind farms

Exilion Tuuli
Completion: 2023

Suvic will carry out the foundation contract for Isokangas-Palokangas wind farms in Ii. The project includes 17 foundations, of which 16 are implemented as rock anchor foundations and 1 as a gravity foundation. The estimated annual production of the wind farm complex will be around 320,000 MWh.

Viiatti wind farms Viiatti wind farms

Viiatti wind farms

Valrea
Completion: 2023-2024

Suvic works as the main contractor in the Kalistanneva and Matkussaari wind farms in Kurikka. The projects are separate entities, of which the Kalistanneva wind farm includes 30 power plants and the Matkussaari wind farm 27 power plants. The contracts also include the construction and renovation of hardstands and roads, the entire substation and the cabling of the internal grid. The combined power of the wind farms is 313.5 MW.

Lakari PV solar plant Lakari PV solar plant

Lakari PV solar plant

CPC Finland
Completion: 2023-2024

Suvic is building a 32 MW solar power plant in Lakari, Rauma with the Solar+ concept, the production of which is estimated to be 32,000 MWh per year. The surface area is about 40 hectares and it is estimated to be in production at the beginning of 2024.

Completed projects

Merkkikallio wind farm Vaasa

OX2
Completion: 2022

Suvic was in charge of the infrastructure construction of the wind farm, including roads, cabling, and foundations. There are 15 power plants in the area, with a nominal power of 5.5 MW for each power plant, and the wingtip runs at a maximum of 240 meters.

Puutikangas wind farm Sievi

OX2
Completion: 2022

Suvic was responsible for the construction of the project's infrastructure, which included the wind farm road, hardstands, foundations, and cabling. Suvic was also responsible for the design of these units. The 8 wind turbines have a total height of 240 m and a total capacity of 44 MW.

Torvenkylä wind farm Kalajoki

Eneriequelle Gmbh
Completion: 2022

For Suvic, the 7 turbine project included the entire infrastructure construction. Unlike in common foundations, over 8-meter concrete elevations were built on top of the foundations to improve the wind farm's electricity production.

Metsälamminkangas wind farm Vaala

OX2
Completion: 2021

Suvic was in charge of the earthworks, foundations, and internal cabling of the wind farm located in Vaala, Northern Ostrobothnia. The wind farm was the third largest in Finland, and it consisted of 24 wind turbines. Suvic started working in Vaala in April 2020, and its part in the project was largely finished during spring 2021.

Karhunnevankangas wind farm Pyhäjoki

wpd Finland
Completion: 2021

Suvic was responsible for the construction of the project's infrastructure, which included the wind farm road, hardstands, foundations, and cabling. Suvic was also responsible for the design of these units. The 8 wind turbines had a total height of 240 m and a total capacity of 44 MW.

Lakiakangas 3 wind farm Isojoki

CPC Finland | Helen
Completion: 2021

For Suvic Oy, the project included the design of foundations of wind turbines and the internal grid with their implementations. The wind farm consists of 20 4.3 MW wind turbines with a total capacity of 86 MW.

Nuolivaara wind farm Kemijärvi

wpd Finland
Completion: 2021

Suvic was responsible for building the foundations. A total of 17 wind turbines were built in the wind farm. The power plants planned in the area have a capacity of 5-6 MW and a total height of 250 meters.

Vermon AWHP Espoo

Fortum
Completion: 2021

Suvic built the foundations for the air-to-water heat pump plant in Vermo. Suvic executed the project management during the civil engineering and foundation work.

  • OX2

    "Suvic is working with us in building a wind farm that consists of two sites, one in Långmossa and the other in Ribäcken. Suvic’s part of the project includes infrastructure for the wind farm, which will have 12 turbines and a total power of 52.5 MW”

    Suvic is in charge of the entire wind farm’s infrastructure on a turnkey basis, including earthmoving, foundations, the electrical grid, telecommunications network and the substation. It is a large undertaking. We are satisfied with the cooperation model and trust in Suvic’s expertise to get the job done as agreed

    Pasi Tammivaara, Project Manager, OX2
  • Fortum Power and Heat Oy

    Our new bio heat plant in Kivenlahti will be completed by 2020, and it will replace the old coal boiler at Suomenoja. Building the plant is a significant step towards Espoo’s carbon-neutral district heat production. The new heat plant is located in the current plant area in Kivenlahti, which already produces district heat with two wood pellet boilers”

    Suvic is operating with the project management contract model for the project. Together, we are developing a concept from the plant that we could use at other sites as well”

    Olli Heinonen, Project Manager, Fortum Power and Heat Oy

    Elektroniikkatie 14
    90590 Oulu, Finland
    +358 20 741 8840

    Billing

    Please send invoices preferably by e-invoice. The invoice must include the site number and code number (littera) as a reference. The invoice should be addressed to each site separately. We apply a reverse charge to VAT for the purchase of construction services.

    E-invoice address: 003728198741
    Operator: Maventa (EDI code 003721291126)
    Email: This email address is being protected from spambots. You need JavaScript enabled to view it.

    By mail:
    Suvic Oy
    28198741
    PL 100
    80020 Kollector Scan